首页 > PMP题库 发布时间:2023-06-27 15:35:56

pmp考试练习题


1. Which of the following is NOT a process in the Project Integration Management knowledge area?

A. Develop Project Charter
B. Develop Project Management Plan
C. Direct and Manage Project Work
D. Monitor and Control Project Work

Answer: D

2. Which of the following is NOT a tool or technique used in the Develop Project Charter process?

A. Expert judgment
B. Project selection methods
C. Project management information system
D. Project management plan

Answer: D

3. Which of the following is NOT a component of the Project Management Plan?

A. Project scope statement
B. Project schedule
C. Project budget
D. Project charter

Answer: D

4. Which of the following is NOT a process in the Project Scope Management knowledge area?

A. Plan Scope Management
B. Collect Requirements
C. Define Scope
D. Monitor and Control Scope

Answer: D

5. Which of the following is a tool or technique used in the Collect Requirements process?

A. Project management plan
B. Expert judgment
C. Project charter
D. Project scope statement

Answer: B

6. Which of the following is NOT a process in the Project Time Management knowledge area?

A. Plan Schedule Management
B. Define Activities
C. Develop Schedule
D. Monitor and Control Schedule

Answer: B

7. Which of the following is a tool or technique used in the Develop Schedule process?

A. Schedule network analysis
B. Project management plan
C. Expert judgment
D. Project charter

Answer: A

8. Which of the following is NOT a process in the Project Cost Management knowledge area?

A. Plan Cost Management
B. Estimate Costs
C. Determine Budget
D. Monitor and Control Costs

Answer: D

9. Which of the following is a tool or technique used in the Estimate Costs process?

A. Project management plan
B. Expert judgment
C. Cost aggregation
D. Project charter

Answer: C

10. Which of the following is NOT a process in the Project Quality Management knowledge area?

A. Plan Quality Management
B. Perform Quality Assurance
C. Control Quality
D. Monitor and Control Quality

Answer: B

11. Which of the following is a tool or technique used in the Plan Quality Management process?

A. Quality metrics
B. Project management plan
C. Expert judgment
D. Project charter

Answer: C

12. Which of the following is NOT a process in the Project Resource Management knowledge area?

A. Plan Resource Management
B. Estimate Activity Resources
C. Acquire Resources
D. Monitor and Control Resources

Answer: B

13. Which of the following is a tool or technique used in the Acquire Resources process?

A. Project management plan
B. Expert judgment
C. Resource calendars
D. Project charter

Answer: C

14. Which of the following is NOT a process in the Project Communications Management knowledge area?

A. Plan Communications Management
B. Manage Communications
C. Control Communications
D. Monitor and Control Communications

Answer: D

15. Which of the following is a tool or technique used in the Plan Communications Management process?

A. Communication requirements analysis
B. Project management plan
C. Expert judgment
D. Project charter

Answer: A

16. Which of the following is NOT a process in the Project Risk Management knowledge area?

A. Plan Risk Management
B. Identify Risks
C. Perform Qualitative Risk Analysis
D. Monitor and Control Risks

Answer: D

17. Which of the following is a tool or technique used in the Identify Risks process?

A. Project management plan
B. Expert judgment
C. Risk register
D. Project charter

Answer: B

18. Which of the following is NOT a process in the Project Procurement Management knowledge area?

A. Plan Procurement Management
B. Conduct Procurements
C. Control Procurements
D. Monitor and Control Procurements

Answer: D

19. Which of the following is a tool or technique used in the Plan Procurement Management process?

A. Project management plan
B. Expert judgment
C. Make-or-buy analysis
D. Project charter

Answer: C

20. Which of the following is NOT a process in the Project Stakeholder Management knowledge area?

A. Identify Stakeholders
B. Plan Stakeholder Engagement
C. Manage Stakeholder Engagement
D. Monitor and Control Stakeholder Engagement

Answer: D

21. Which of the following is a tool or technique used in the Identify Stakeholders process?

A. Project management plan
B. Expert judgment
C. Stakeholder analysis