A. Develop Project Charter
B. Develop Project Management Plan
C. Direct and Manage Project Work
D. Monitor and Control Project Work
Answer: D
2. Which of the following is NOT a tool or technique used in the Develop Project Charter process?
A. Expert judgment
B. Project selection methods
C. Project management information system
D. Project management plan
Answer: D
3. Which of the following is NOT a component of the Project Management Plan?
A. Project scope statement
B. Project schedule
C. Project budget
D. Project charter
Answer: D
4. Which of the following is NOT a process in the Project Scope Management knowledge area?
A. Plan Scope Management
B. Collect Requirements
C. Define Scope
D. Monitor and Control Scope
Answer: D
5. Which of the following is a tool or technique used in the Collect Requirements process?
A. Project management plan
B. Expert judgment
C. Project charter
D. Project scope statement
Answer: B
6. Which of the following is NOT a process in the Project Time Management knowledge area?
A. Plan Schedule Management
B. Define Activities
C. Develop Schedule
D. Monitor and Control Schedule
Answer: B
7. Which of the following is a tool or technique used in the Develop Schedule process?
A. Schedule network analysis
B. Project management plan
C. Expert judgment
D. Project charter
Answer: A
8. Which of the following is NOT a process in the Project Cost Management knowledge area?
A. Plan Cost Management
B. Estimate Costs
C. Determine Budget
D. Monitor and Control Costs
Answer: D
9. Which of the following is a tool or technique used in the Estimate Costs process?
A. Project management plan
B. Expert judgment
C. Cost aggregation
D. Project charter
Answer: C
10. Which of the following is NOT a process in the Project Quality Management knowledge area?
A. Plan Quality Management
B. Perform Quality Assurance
C. Control Quality
D. Monitor and Control Quality
Answer: B

11. Which of the following is a tool or technique used in the Plan Quality Management process?
A. Quality metrics
B. Project management plan
C. Expert judgment
D. Project charter
Answer: C
12. Which of the following is NOT a process in the Project Resource Management knowledge area?
A. Plan Resource Management
B. Estimate Activity Resources
C. Acquire Resources
D. Monitor and Control Resources
Answer: B
13. Which of the following is a tool or technique used in the Acquire Resources process?
A. Project management plan
B. Expert judgment
C. Resource calendars
D. Project charter
Answer: C
14. Which of the following is NOT a process in the Project Communications Management knowledge area?
A. Plan Communications Management
B. Manage Communications
C. Control Communications
D. Monitor and Control Communications
Answer: D
15. Which of the following is a tool or technique used in the Plan Communications Management process?
A. Communication requirements analysis
B. Project management plan
C. Expert judgment
D. Project charter
Answer: A
16. Which of the following is NOT a process in the Project Risk Management knowledge area?
A. Plan Risk Management
B. Identify Risks
C. Perform Qualitative Risk Analysis
D. Monitor and Control Risks
Answer: D
17. Which of the following is a tool or technique used in the Identify Risks process?
A. Project management plan
B. Expert judgment
C. Risk register
D. Project charter
Answer: B
18. Which of the following is NOT a process in the Project Procurement Management knowledge area?
A. Plan Procurement Management
B. Conduct Procurements
C. Control Procurements
D. Monitor and Control Procurements
Answer: D
19. Which of the following is a tool or technique used in the Plan Procurement Management process?
A. Project management plan
B. Expert judgment
C. Make-or-buy analysis
D. Project charter
Answer: C
20. Which of the following is NOT a process in the Project Stakeholder Management knowledge area?
A. Identify Stakeholders
B. Plan Stakeholder Engagement
C. Manage Stakeholder Engagement
D. Monitor and Control Stakeholder Engagement
Answer: D
21. Which of the following is a tool or technique used in the Identify Stakeholders process?
A. Project management plan
B. Expert judgment
C. Stakeholder analysis