1. What is the primary purpose of a project charter?
A. To define the project scope
B. To identify project risks
C. To establish project objectives and goals
D. To create a project schedule

Answer: C

2. Which of the following is NOT a project constraint?
A. Scope
B. Time
C. Cost
D. Quality

Answer: D

3. Which of the following is NOT a project management process group?
A. Planning
B. Execution
C. Monitoring and Controlling
D. Closing

Answer: E (Initiating)

4. Which of the following is NOT a tool or technique used in project cost management?
A. Cost-benefit analysis
B. Earned value management
C. Pareto chart
D. Reserve analysis

Answer: C

5. Which of the following is NOT a tool or technique used in project risk management?
A. Risk identification
B. Risk response planning
C. Risk monitoring and control
D. Pareto chart

Answer: D

6. Which of the following is NOT a tool or technique used in project quality management?
A. Quality control
B. Quality assurance
C. Pareto chart
D. Benchmarking

Answer: C

7. Which of the following is NOT a tool or technique used in project time management?
A. Critical path method
B. Schedule compression
C. Pareto chart
D. Resource leveling

Answer: C

8. Which of the following is NOT a tool or technique used in project scope management?
A. Scope statement
B. Work breakdown structure
C. Pareto chart
D. Scope verification

Answer: C

9. Which of the following is NOT a tool or technique used in project communication management?
A. Communication plan
B. Stakeholder analysis
C. Pareto chart
D. Information distribution

Answer: C

10. Which of the following is NOT a tool or technique used in project procurement management?
A. Procurement documents
B. Source selection criteria
C. Pareto chart
D. Contract types

Answer: C

11. Which of the following is NOT a tool or technique used in project integration management?
A. Project charter
B. Change control system
C. Pareto chart
D. Project management plan

Answer: C

12. Which of the following is NOT a tool or technique used in project human resource management?
A. Organizational charts
B. Resource histograms
C. Pareto chart
D. Staffing management plan

Answer: C

13. Which of the following is NOT a tool or technique used in project stakeholder management?
A. Stakeholder register
B. Stakeholder analysis
C. Pareto chart
D. Communication management plan

Answer: C

14. Which of the following is NOT a tool or technique used in project scope verification?
A. Inspection
B. Acceptance criteria


C. Pareto chart
D. Testing

Answer: C

15. Which of the following is NOT a tool or technique used in project risk response planning?
A. Avoidance
B. Mitigation
C. Pareto chart
D. Transfer

Answer: C

16. Which of the following is NOT a tool or technique used in project quality control?
A. Inspection
B. Control charts
C. Pareto chart
D. Statistical sampling

Answer: C

17. Which of the following is NOT a tool or technique used in project schedule compression?
A. Crashing
B. Fast tracking
C. Pareto chart
D. Resource leveling

Answer: C

18. Which of the following is NOT a tool or technique used in project resource management?
A. Resource histograms
B. Pareto chart
C. Resource leveling
D. Resource assignment matrix

Answer: B

19. Which of the following is NOT a tool or technique used in project stakeholder analysis?
A. Power/interest grid
B. Salience model
C. Pareto chart
D. Stakeholder mapping

Answer: C

20. Which of the following is NOT a tool or technique used in project change control?
A. Configuration management
B. Pareto chart
C. Change control board
D. Change request form

Answer: B

21. Which of the following is NOT a tool or technique used in project scope definition?
A. Product analysis
B. Pareto chart
C. Requirements documentation
D. Stakeholder analysis

Answer: B

22. Which of the following is NOT a tool or technique used in project stakeholder engagement?
A. Communication methods
B. Pareto chart
C. Stakeholder management plan
D. Stakeholder engagement assessment matrix

Answer: B

23. Which of the following is NOT a tool or technique used in project procurement planning?
A. Make-or-buy analysis
B. Pareto chart
C. Procurement management plan
D. Source selection criteria

Answer: B

24. Which of the following is NOT a tool or technique used in project monitoring and controlling?
A. Pareto chart
B. Performance reporting
C. Change control
D. Variance analysis

Answer: A

25. Which of the following is NOT a tool or technique used in project closure?
A. Pareto chart
B. Lessons learned
C. Project archives
D. Transition planning

Answer: A