好的,以下是一些PMP考试的样例题目:
1. Which of the following is NOT a tool or technique of the Plan Quality Management process?
A. Cost-benefit analysis
B. Benchmarking
C. Design of experiments
D. Flowcharting
2. Which of the following is NOT a component of the Project Charter?
A. Project purpose or justification
B. Project objectives and success criteria
C. Project scope
D. Project schedule
3. Which of the following is NOT a tool or technique of the Control Quality process?
A. Inspection
B. Statistical sampling
C. Pareto chart
D. Resource leveling
4. Which of the following is NOT a tool or technique of the Control Scope process?
A. Variance analysis
B. Performance reporting
C. Change control system
D. Expert judgment
5. Which of the following is NOT a tool or technique of the Control Schedule process?
A. Schedule compression
B. Resource leveling
C. Critical path method
D. Pareto chart