1. Which of the following is NOT a key component of project management?

A. Scope management
B. Time management
C. Cost management
D. Quality management
E. Customer management

Answer: E

2. Which of the following is NOT a tool or technique used in project cost management?

A. Cost-benefit analysis
B. Earned value management
C. Cost of quality
D. Cost estimating
E. Pareto analysis

Answer: E

3. Which of the following is NOT a process in project risk management?

A. Risk identification
B. Risk analysis
C. Risk response planning
D. Risk monitoring and control
E. Risk avoidance

Answer: E

4. Which of the following is NOT a type of project constraint?

A. Scope
B. Time
C. Cost
D. Quality
E. Risk

Answer: E

5. Which of the following is NOT a process in project procurement management?

A. Plan procurement management
B. Conduct procurement
C. Control procurement
D. Close procurement
E. Monitor procurement

Answer: E

6. Which of the following is NOT a tool or technique used in project schedule management?

A. Critical path method
B. Gantt chart
C. Resource leveling
D. Monte Carlo analysis
E. Pareto analysis

Answer: E

7. Which of the following is NOT a process in project scope management?

A. Plan scope management
B. Collect requirements
C. Define scope
D. Control scope
E. Monitor scope

Answer: E

8. Which of the following is NOT a tool or technique used in project quality management?

A. Quality control charts
B. Statistical sampling
C. Benchmarking
D. Pareto analysis
E. Resource leveling

Answer: E

9. Which of the following is NOT a process in project integration management?

A. Develop project charter
B. Develop project management plan
C. Direct and manage project work
D. Monitor and control project work
E. Close project or phase

Answer: E

10. Which of the following is NOT a tool or technique used in project communication management?

A. Communication models
B. Information management systems
C. Stakeholder analysis
D. Performance reporting
E. Pareto analysis

Answer: E

11. Which of the following is NOT a process in project stakeholder management?

A. Identify stakeholders
B. Plan stakeholder engagement
C. Manage stakeholder engagement
D. Control stakeholder engagement
E. Monitor stakeholder engagement

Answer: E

12. Which of the following is NOT a tool or technique used in project human resource management?

A. Organizational charts
B. Resource leveling
C. Team-building activities
D. Performance appraisals
E. Pareto analysis

Answer: E

13. Which of the following is NOT a process in project scope management?

A. Plan scope management
B. Collect requirements
C. Define scope
D. Create WBS
E. Monitor scope

Answer: E

14. Which of the following is NOT a tool or technique used in project risk management?

A. Risk probability and impact assessment
B. Risk categorization
C. Risk response planning
D. Risk avoidance
E. Pareto analysis

Answer: E

15. Which of the following is NOT a process in project time management?

A. Plan schedule management
B. Define activities
C. Sequence activities
D. Estimate activity resources
E. Monitor and control project work

Answer: E

16. Which of the following is NOT a tool or technique used in project cost management?

A. Cost-benefit analysis
B. Cost estimating
C. Cost of quality
D. Pareto analysis
E. Resource leveling

Answer: D

17. Which of the following is NOT a process in project quality management?

A. Plan quality management
B. Perform quality assurance
C. Control quality
D. Monitor quality
E. Pareto analysis

Answer: E

18. Which of the following is NOT a tool or technique used in project procurement management?

A. Make-or-buy analysis
B. Contract types
C. Bidder conferences
D. Pareto analysis
E. Source selection criteria

Answer: D

19. Which of the following is NOT a process in project integration management?

A. Develop project charter
B. Develop project management plan
C. Direct and manage project work
D. Monitor and control project work
E. Pareto analysis

Answer: E

20. Which of the following is NOT a tool or technique used in project communication management?

A. Communication models
B. Information management systems
C. Stakeholder analysis
D. Pareto analysis
E. Performance reporting

Answer: D