A. Scope management
B. Time management
C. Cost management
D. Quality management
E. Customer management
Answer: E
2. Which of the following is NOT a tool or technique used in project cost management?
A. Cost-benefit analysis
B. Earned value management
C. Cost of quality
D. Cost estimating
E. Pareto analysis
Answer: E
3. Which of the following is NOT a process in project risk management?
A. Risk identification
B. Risk analysis
C. Risk response planning
D. Risk monitoring and control
E. Risk avoidance
Answer: E
4. Which of the following is NOT a type of project constraint?
A. Scope
B. Time
C. Cost
D. Quality
E. Risk
Answer: E
5. Which of the following is NOT a process in project procurement management?
A. Plan procurement management
B. Conduct procurement
C. Control procurement
D. Close procurement
E. Monitor procurement
Answer: E
6. Which of the following is NOT a tool or technique used in project schedule management?
A. Critical path method
B. Gantt chart
C. Resource leveling
D. Monte Carlo analysis
E. Pareto analysis
Answer: E
7. Which of the following is NOT a process in project scope management?
A. Plan scope management
B. Collect requirements
C. Define scope
D. Control scope
E. Monitor scope
Answer: E
8. Which of the following is NOT a tool or technique used in project quality management?
A. Quality control charts
B. Statistical sampling
C. Benchmarking
D. Pareto analysis
E. Resource leveling
Answer: E
9. Which of the following is NOT a process in project integration management?
A. Develop project charter
B. Develop project management plan
C. Direct and manage project work
D. Monitor and control project work
E. Close project or phase
Answer: E
10. Which of the following is NOT a tool or technique used in project communication management?
A. Communication models
B. Information management systems
C. Stakeholder analysis
D. Performance reporting
E. Pareto analysis
Answer: E

11. Which of the following is NOT a process in project stakeholder management?
A. Identify stakeholders
B. Plan stakeholder engagement
C. Manage stakeholder engagement
D. Control stakeholder engagement
E. Monitor stakeholder engagement
Answer: E
12. Which of the following is NOT a tool or technique used in project human resource management?
A. Organizational charts
B. Resource leveling
C. Team-building activities
D. Performance appraisals
E. Pareto analysis
Answer: E
13. Which of the following is NOT a process in project scope management?
A. Plan scope management
B. Collect requirements
C. Define scope
D. Create WBS
E. Monitor scope
Answer: E
14. Which of the following is NOT a tool or technique used in project risk management?
A. Risk probability and impact assessment
B. Risk categorization
C. Risk response planning
D. Risk avoidance
E. Pareto analysis
Answer: E
15. Which of the following is NOT a process in project time management?
A. Plan schedule management
B. Define activities
C. Sequence activities
D. Estimate activity resources
E. Monitor and control project work
Answer: E
16. Which of the following is NOT a tool or technique used in project cost management?
A. Cost-benefit analysis
B. Cost estimating
C. Cost of quality
D. Pareto analysis
E. Resource leveling
Answer: D
17. Which of the following is NOT a process in project quality management?
A. Plan quality management
B. Perform quality assurance
C. Control quality
D. Monitor quality
E. Pareto analysis
Answer: E
18. Which of the following is NOT a tool or technique used in project procurement management?
A. Make-or-buy analysis
B. Contract types
C. Bidder conferences
D. Pareto analysis
E. Source selection criteria
Answer: D
19. Which of the following is NOT a process in project integration management?
A. Develop project charter
B. Develop project management plan
C. Direct and manage project work
D. Monitor and control project work
E. Pareto analysis
Answer: E
20. Which of the following is NOT a tool or technique used in project communication management?
A. Communication models
B. Information management systems
C. Stakeholder analysis
D. Pareto analysis
E. Performance reporting
Answer: D