A. Temporary
B. Unique
C. Ongoing
D. Progressive elaboration
Answer: C
2. Which of the following is NOT a process in the Project Integration Management knowledge area?
A. Develop Project Charter
B. Develop Project Management Plan
C. Direct and Manage Project Work
D. Monitor and Control Project Work
Answer: D
3. Which of the following is NOT a tool or technique used in the Develop Project Charter process?
A. Expert judgment
B. Project selection methods
C. Project management information system
D. Project management plan
Answer: D
4. Which of the following is NOT a component of the Project Management Plan?
A. Project scope statement
B. Project schedule
C. Project budget
D. Project charter
Answer: D
5. Which of the following is NOT a tool or technique used in the Direct and Manage Project Work process?
A. Expert judgment
B. Project management information system
C. Change control tools
D. Project management plan
Answer: C
6. Which of the following is NOT a process in the Project Scope Management knowledge area?
A. Plan Scope Management
B. Collect Requirements
C. Define Scope
D. Monitor and Control Scope
Answer: D
7. Which of the following is NOT a tool or technique used in the Plan Scope Management process?
A. Expert judgment
B. Project management information system
C. Project charter
D. Stakeholder analysis
Answer: C
8. Which of the following is NOT a component of the Project Scope Statement?
A. Project objectives
B. Project deliverables
C. Project assumptions
D. Project budget
Answer: D
9. Which of the following is NOT a process in the Project Time Management knowledge area?
A. Plan Schedule Management
B. Define Activities
C. Estimate Activity Durations
D. Monitor and Control Schedule
Answer: D
10. Which of the following is NOT a tool or technique used in the Plan Schedule Management process?
A. Expert judgment
B. Project management information system
C. Schedule network analysis
D. Project charter
Answer: D